Your legal remedies when a builder abandons work, doesn't finish, or does poor quality work. Learn about reasonable care and skill, retention rights, and small claims procedures.
Supply of Goods and Services Act 1982 s.13 requires builders exercise reasonable care and skill. Incomplete or poor work is breach of contract. You can withhold final payment until completion. Retention clauses (withholding 5-10% until end) are common but must be fair. You can hire another builder and deduct costs from what you owe. Small claims court (under £100,000) is straightforward route; most cases succeed. Builder cannot claim payment for incomplete work. Document everything (photos, messages, timelines) for court.
Take photos of incomplete/poor work. Keep all communications (emails, texts, calls). Note completion date promised vs. actual. Get a quote from another builder for correction costs. This becomes your claim value.
Email builder: "Work is incomplete/below standard. Supply of Goods and Services Act 1982 s.13 requires reasonable care. Correct defects within 14 days or I will hire another contractor and deduct costs from payment owed." Set clear deadline.
Do not pay remaining balance. If builder refuses to fix, hire another contractor, get invoice, deduct from what you owe. If still disputes, file small claims for the remaining shortfall or original contract value minus costs to complete.
Stop paying immediately. Builder cannot claim payment for uncompleted work. Hire another contractor, get completion quote, sue for difference. Withhold all remaining payments. Small claims will award you the cost to complete minus any value of partial work.
Breach of "reasonable care and skill" standard. Document defects. Get repair quotes. Demand builder correct defects; if refused, hire another contractor and deduct costs from final payment owed. If builder sues, defend in small claims citing defects and cost to remedy.
If contract states completion date, breach if not met. You can withhold final payment and claim liquidated damages (pre-agreed delay penalty in contract) if included. If no penalty clause, claim reasonable damages for your inconvenience (rental of temporary housing, etc.) if applicable.
Retention (e.g. 10% withheld until end) is fair if amount is reasonable. But once work is complete, retention must be released. If builder refuses, sue for the retention amount in small claims. Court will order release once work is proven complete.
Refuse. Builder cannot claim payment for breach. You owe only for completed, quality work. If builder sues you, defend by citing incomplete work and cost to complete. Small claims will rule in your favour if evidence clear.
Courts test against average tradesperson standard for the price. If you paid premium price, higher standard expected. If budget job, lower expectation. Get expert opinion (another builder's assessment) as evidence. Court will compare actual work to standard for similar price/scope.
File small claims and recover your costs to complete the job.
Start Your Builder Dispute Claim